In the interests of release predictability and transparency, here is the roadmap for current and future OpenSocial specification development.
For each major release of OpenSocial, we will publish an Implementor's Draft where all major specification changes will be incubated until such time that the community has made significant implementations of these incubating changes and provided feedback. While there is wide agreement in principal, the Community still needs to define and vote on this new process. Once established it will be documented in the specification process.
The OpenSocial Foundation will plan for a yearly specification release cadence on the OpenSocial specification.
Date |
Milestone |
---|---|
Early April 2012 |
First Draft |
June 2012 |
Final Draft |
July 2012 |
Voting |
OSCON, July 2012 |
Final |
List of Changes: Spec Changes - v2.5
Date |
Milestone |
---|---|
May - Sept 2012 |
Call for New Features |
May 12 - Jan 13 |
Monthly Implementer's Draft |
January 2013 |
Release Candidate 1 |
February 2013 |
Release Candidate 2 |
March 2013 |
Final |
List of Changes: Spec Changes - v3.0